On Thursday 13th, the official electrification of the La Planicie-Industriales 220kV Line was carried out by ISA Rep. SEMI was selected for the engineering, procurement and construction of the 5.4km double circuit underground power line. The project was completed two months ahead of schedule, despite the challenge posed by the line crossing the city of Lima – it was even necessary to create a tunnel to cross one of the main roads of the city.

For more information: https://www.youtube.com/watch?v=l2qpyy0RISs

 